# Distribution networks: what to measure at low voltage with solar, batteries and EVs

https://amperis.com/en/resources/articles/webinars-distribution-networks/

> A home EV charger adds another 2.5 kW per household. What a low-voltage monitor measures and what is worth watching on each transformer.

Most distribution networks run almost blind: few sensors, often no meters, and faults that cannot be located quickly. Distributed generation has arrived on top of that network. Average household demand is planned at about 2.5 kW, a home EV charger adds as much again and rapid chargers reach 350 kW, while solar and batteries reverse the flow at the transformer. This video explains what can be measured at low voltage and what is worth watching on each transformer.

## Key points

- A low-voltage monitor at the distribution transformer measures three voltages and four currents, power quality, events and temperature. With that it answers safety (loss of neutral), reliability, planning, hosting capacity for chargers and solar, and revenue (theft and illegal connections) at once.
- What utilities ask for is specific: knowing which phase each customer is on before disconnecting one on life support, knowing a line is down before anyone calls, and how much rooftop solar the network can really take.
- What to watch depends on the transformer: on a pole-mounted unit, little more than basic overheating; on a ground-mounted one, oil level, overheating, moisture and two gases; on a large one, 3- or 5-gas dissolved gas analysis, partial discharge and pressure rise.
- Tank pressure is the earliest indicator of an internal arc, whose energy is arc voltage times current times a clearing time of four or five cycles. Measuring it in real time reduces the fire risk, but does not remove it.
- The economics depend on each network: failure rates differ by an order of magnitude between regions, and regulatory penalties and safety usually decide the case, not the cost of repairing the transformer.

## The network nobody can see

The starting point is uncomfortable. There is little or no real-time data: few sensors, and often no smart meters. Faults and outages cannot be located quickly, so they cost more. Assets fail without warning, and some of those failures reach the public. Hidden capacity cannot be found, so it cannot be used. And power theft cannot be identified at all.

## The load stopped behaving

The planning figure for an average house is about 2.5 kW, and an average home electric-car charger draws about the same again. Public chargers run from 2.5 to 7 kW, and fast chargers up to 350 kW. Meanwhile solar and storage push power the other way through the transformer. The result is overloading, overvoltage and power quality complaints.

Behind it sits a physical problem. The grid is a constant balance between demand and generation, and renewable output follows the weather, not a dispatch instruction. Traditional plant ramps at tens of megawatts a minute; diversity across regions firms up the average, but it pushes the burden onto the network that has to move the energy, and storage and demand management cover the short dips.

## One box, several answers

A low-voltage monitor at the distribution transformer measures three voltages and four currents, power quality and harmonics, event waveforms captured when something happens, and the temperature at the transformer. From that it answers questions about:

- **Safety:** failing assets near people, and loss of neutral.
- **Reliability:** locating faults fast and finding incipient ones.
- **Planning:** real capacity, and where the constraints are.
- **Hosting capacity:** for chargers, solar and storage.
- **Revenue:** theft and illegal connections.

Answering several questions with one device is what makes it affordable.

## What utilities actually asked for

Five distribution utilities that installed three-phase LV monitors at their distribution transformers set out needs more practical than any specification. The first has little access to smart meters and wants to know the network’s capacity, to find out how much rooftop solar it can take. The second wants to know which phase each customer is on, so that customers on life support are not disconnected by accident, and to detect when a single connection or a line in a remote area is down before the customer calls. The third has pillar box fires and wants LV monitoring at the feeders to pick up problems before they become fires. The fourth wants to find network capacity for EV chargers and limit their impact. The fifth is rolling out LV monitors state-wide to improve safety, understand loading capacity and plan ahead. In Australia, Jemena’s Dynamic Electric Vehicle Charging Trial, supported by ARENA, already uses LV monitoring data to control EV charging.

## It is not the technology

Distribution transformers fail in much the same ways as large ones, but they cannot be monitored in the same way. The limit is access points, space, power, communications and mounting — in other words, the physical design of the unit itself. Failure modes may be equal; visibility is not. So what is realistic depends on the size of the unit:

Measurement | Pole mount | Pad mount | Large

Oil level | rare | yes | yes
Overheating | basic | yes | yes
Moisture ingress | rarely practical | possible | possible
Internal arcing | indirect | two-gas | 3 or 5-gas DGA
Partial discharge | no | rarely | possible
Pressure build-up | rare | possible | standard

The best strategy is not measuring everything; it is measuring what matters on that particular transformer.

## Pressure and fire

Pressure inside the tank is the earliest indicator of an internal arc. Arc energy is arc voltage times arc current times time, and the time is usually the fault clearing time, four to five cycles. Arc voltage depends on the arc length and the electrode shape: an inter-turn fault is low energy, while a line-to-tank fault is the highest. The main source of oxygen for a fire is the air that enters after the tank ruptures. Real-time pressure data mitigates the risk of fire; it does not prevent it.

## Power quality is no longer a specialist topic

It has become part of ordinary asset management, across four areas: voltage (swells, sags, over- and undervoltage), loading (current, kVA, peak demand), harmonics (overheating, losses, nuisance tripping) and imbalance (uneven loading, neutral current).

## Is it worth it? Not the same answer everywhere

Where units are cheap and locally made, a failure is replaced, not prevented. Where they are imported, the replacement cost and the delay change the sum. Failure rates differ by an order of magnitude between regions, regulatory penalties and incentives often decide it rather than the repair bill, and the financial impact of an outage goes well beyond the replacement. Where the consequences are low, monitoring is rare, and reasonably so. The case has to be made asset by asset.

## Five things to take away

- The distribution network is close to blind, and that is the root problem.
- Distributed generation and charging have made the old assumptions wrong.
- The obstacle to monitoring is physical access, not technology.
- Measure what matters on that unit, rather than everything everywhere.
- Justify it on penalties, safety and capacity, not on the transformer’s price.

## Related equipment

For power quality at the transformer and in the network, see our [power quality analysers](https://amperis.com/en/products/electric-panel-multimeters/), including the [APQM series](https://amperis.com/en/products/electric-panel-multimeters/serie-apqm/). For the transformers themselves, see [transformer testing and monitoring](https://amperis.com/en/products/transformers-testing/). To talk through monitoring for your network, [contact our engineers](https://amperis.com/en/contact/).