WEBVTT

00:00:00.533 --> 00:00:01.434
From Amperis:

00:00:01.474 --> 00:00:07.373
how the GRIDSCAN 5000 is installed, wired,
configured, and what happens inside it.

00:00:10.287 --> 00:00:14.537
First, the rules. Installation and
maintenance must be carried out by

00:00:14.577 --> 00:00:18.206
certified installers authorised
to work on the transformer.

00:00:18.246 --> 00:00:21.750
Switch off electrical power
before making any connection,

00:00:21.790 --> 00:00:24.051
and make the ground connection first.

00:00:28.964 --> 00:00:33.780
What the job needs: a wrench, a suitable
4 conductor cable, thread sealant,

00:00:33.820 --> 00:00:37.794
a 3 quarter inch valve, and a 10
watt industrial power supply.

00:00:42.767 --> 00:00:47.651
Where it goes. As close to the tank
as possible, on a valve of 3 quarters

00:00:47.691 --> 00:00:51.361
of an inch or larger, with
any pipework of at least one

00:00:51.401 --> 00:00:55.071
inch inside diameter, and
away from turbulent oil flow.

00:00:58.402 --> 00:01:03.155
Orientation matters. In oil the
monitor mounts horizontally,

00:01:03.195 --> 00:01:07.789
so that no air bubble can form
around the sensing element.

00:01:07.829 --> 00:01:13.620
Angles from 180 to 360 degrees are
acceptable; one to 179 degrees is not.

00:01:13.660 --> 00:01:18.014
In the gas space, horizontal
or vertical are both fine.

00:01:22.316 --> 00:01:23.931
The mechanical connection.

00:01:23.971 --> 00:01:27.752
Keep the red cap on until the
last moment, seal the threads,

00:01:27.792 --> 00:01:31.317
and put the wrench on the
housing closest to the thread.

00:01:31.357 --> 00:01:35.902
Standard torque for a 3 quarter inch
NPT fitting is about 50 pound feet.

00:01:35.942 --> 00:01:37.175
Do not over tighten.

00:01:44.692 --> 00:01:48.516
On an oil calibrated unit, the
trapped air has to come out.

00:01:48.556 --> 00:01:53.494
Close everything, open the bleed, crack
the transformer valve until oil runs

00:01:53.534 --> 00:01:58.734
without bubbles, close the bleed, then
open the valve fully and check for leaks.

00:02:04.246 --> 00:02:06.702
The electrical side is one cable.

00:02:06.742 --> 00:02:12.527
Four conductors carry DC power and two
wire RS-485 to the customer equipment,

00:02:12.567 --> 00:02:16.006
with the cable shield
earthed at one end only.

00:02:20.701 --> 00:02:26.534
The pin out of the M 12 connector:
pin one, DC power, brown.

00:02:26.574 --> 00:02:34.659
Pin two, DC ground, white. Pin 3, RS-485
data plus, blue. Pin 4, data minus, black.

00:02:42.027 --> 00:02:43.179
Power and bus.

00:02:43.219 --> 00:02:49.140
An industrial, substation rated supply
of 12 to 48 volts DC, 10 watts.

00:02:49.180 --> 00:02:52.717
The RS-485 input is galvanically isolated,

00:02:52.757 --> 00:02:58.848
and a 120 ohm termination resistor is
already fitted inside the monitor.

00:03:03.041 --> 00:03:08.222
Power it up, and be patient. The monitor
runs a self test, restores its settings,

00:03:08.262 --> 00:03:10.801
starts measuring, and calibrates itself.

00:03:10.841 --> 00:03:13.637
On a new installation
that sequence can take

00:03:13.677 --> 00:03:16.731
up to 16 hours before the
readings are accurate.

00:03:22.524 --> 00:03:26.730
Inside, it is simpler than a
chromatograph and that is the point.

00:03:26.770 --> 00:03:30.649
At the tip, the solid state
palladium alloy sensing element.

00:03:30.689 --> 00:03:33.000
Behind it, a hermetic glass to metal

00:03:33.040 --> 00:03:36.201
feedthrough and gaskets
form a gas tight barrier.

00:03:36.241 --> 00:03:40.708
Then the 5th generation electronics,
with an isolated regulator and a

00:03:40.748 --> 00:03:45.607
galvanically isolated bus, and a
supercapacitor that keeps the clock alive.

00:03:51.183 --> 00:03:53.329
In service it runs its own routine.

00:03:53.369 --> 00:03:57.826
Oil temperature about once an hour
for temperature compensated readings,

00:03:57.866 --> 00:04:01.760
and every 10 hours or so a
reference cycle of around two hours,

00:04:01.800 --> 00:04:06.944
during which the monitor holds its last
hydrogen value. No user action is required.

00:04:12.350 --> 00:04:15.355
The ScanH two utility
does the commissioning.

00:04:15.395 --> 00:04:19.009
It connects over RS-485 or
through an Ethernet bridge,

00:04:19.049 --> 00:04:22.663
sets the protocol and address,
synchronises the clock,

00:04:22.703 --> 00:04:28.076
selects the insulating liquid, and reads
or writes the whole configuration file.

00:04:32.443 --> 00:04:33.763
And what to poll.

00:04:33.803 --> 00:04:39.281
Registers 0 and 1 for hydrogen, and
the high word must be read first.

00:04:39.321 --> 00:04:41.760
Register 8 for oil temperature.

00:04:41.800 --> 00:04:45.839
Register 111 for status,
and 112 and 13 for errors.

00:04:50.913 --> 00:04:53.545
GRIDSCAN 5000, from Amperis.