What comes in the case,
what every cable is for,

00:00:03.547 --> 00:00:07.116
and how the TRT is connected
to each kind of transformer.

00:00:09.860 --> 00:00:13.068
Start with what is in the
case, because two of these are

00:00:13.108 --> 00:00:16.433
easy to leave behind and both
are needed on the first job.

00:00:19.515 --> 00:00:23.785
On the panel, the two blocks on the
right are the whole measurement.

00:00:23.825 --> 00:00:28.095
Four H sockets for the high voltage
winding, 4 X sockets for the low

00:00:28.135 --> 00:00:32.786
voltage winding, colour coded so a lead
can only sensibly go in one place.

00:00:37.541 --> 00:00:42.784
And the rest of the panel: power, the earth
stud, the tap changer control connector,

00:00:42.824 --> 00:00:46.872
the flash drive and the ports for
the PC, and the emergency stop.

00:00:51.336 --> 00:00:57.705
The leads come as two sets: an H winding
set and an X winding set, 4 cables each,

00:00:57.745 --> 00:01:01.503
10 metres as standard,
terminated in TTA clamps.

00:01:01.543 --> 00:01:07.358
5, 15 and 20 metre sets are available,
and extension sets on top of those.

00:01:10.345 --> 00:01:13.179
A three-phase transformer
is the ordinary case,

00:01:13.219 --> 00:01:18.255
and the point of the instrument is that it
is connected only once. The earth first.

00:01:18.295 --> 00:01:21.374
Then the 4 H cables onto
the high voltage bushings,

00:01:21.414 --> 00:01:24.126
and the 4 X cables onto
the low voltage side.

00:01:24.166 --> 00:01:28.285
Every vector group is then tested
without touching the hookup again.

00:01:33.658 --> 00:01:37.218
A single-phase transformer
uses part of the same set:

00:01:37.258 --> 00:01:39.255
two H cables and two X cables.

00:01:39.295 --> 00:01:42.923
Nothing else is needed, and
nothing else is connected.

00:01:45.746 --> 00:01:50.428
A phase-shifting transformer is the
one that looks intimidating and is not.

00:01:50.468 --> 00:01:54.395
It is a series transformer and
a shunt transformer in one tank,

00:01:54.435 --> 00:01:58.487
and the instrument is connected
to both sets of bushings at once,

00:01:58.527 --> 00:02:01.824
exactly as it would be on
any other three-phase unit.

00:02:04.443 --> 00:02:06.778
And a capacitive voltage transformer,

00:02:06.818 --> 00:02:10.759
which needs more voltage than
the instrument makes on its own.

00:02:10.799 --> 00:02:15.510
The CVT 20 sits between them and takes
the test voltage up to 5 kilovolts.

00:02:18.961 --> 00:02:21.624
The handheld version is
connected the same way,

00:02:21.664 --> 00:02:25.938
with clamps instead of connectors, and
it is the one that goes up the pole.

00:02:25.978 --> 00:02:28.986
Here it is on a three-phase
distribution transformer.

00:02:32.243 --> 00:02:37.260
A current transformer is the case people
get wrong, and it is worth saying slowly.

00:02:37.300 --> 00:02:42.256
ACT has almost all its turns on the
secondary and only one or two on the primary.

00:02:42.296 --> 00:02:46.697
So the X cables go to the primary,
and the H cables go to the secondary.

00:02:46.737 --> 00:02:51.261
And when there are no primary terminals
at all, which is most of them once

00:02:51.301 --> 00:02:56.134
installed, the X cables are slid through
the core and short-circuited together.

00:02:56.174 --> 00:02:58.724
That single pass is the primary: one turn.

00:03:07.446 --> 00:03:11.420
One more hookup worth knowing,
because it saves a whole second visit.

00:03:11.460 --> 00:03:15.724
The turns ratio tester and the winding
ohmmeter share the same test leads,

00:03:15.764 --> 00:03:19.680
so both can be connected to the
transformer at the same time and the

00:03:19.720 --> 00:03:23.577
two tests run one after the other
without anybody touching a clamp.

00:03:29.794 --> 00:03:32.281
The tap changer control unit is built in,

00:03:32.321 --> 00:03:35.979
and it is what turns a two-person
job into a one-person job.

00:03:36.019 --> 00:03:38.752
The 5 metre control
cable goes from the panel

00:03:38.792 --> 00:03:41.772
to the tap changer, and
the instrument drives it.

00:03:45.067 --> 00:03:47.780
And the test itself,
once everything is on.

00:03:47.820 --> 00:03:50.980
Enter the nameplate, pick
the vector diagram, run,

00:03:51.020 --> 00:03:55.141
and read the deviation rather than
doing the arithmetic yourself.

00:03:59.912 --> 00:04:03.131
On the screen the sweep comes
out as a chart rather than

00:04:03.171 --> 00:04:06.447
a column of numbers, with the
tolerance band drawn on it.

00:04:06.487 --> 00:04:10.928
A tap that steps outside the band is
visible without reading a single figure.

00:04:14.856 --> 00:04:17.225
Transformer testing, from Amperis.